November 12, 2026
Two construction projects are underway on Timnath's roads this month, and they are on very different schedules. The Town's new roundabout on Timnath Parkway was scheduled to open to two-way traffic on Friday, Nov. 6. The day after that, crews closed Colorado Boulevard north of Wildwing Drive through Nov. 26. The roundabout belongs to a Town project that is supposed to be substantially complete by the end of 2026. The Colorado Boulevard closure belongs to the City of Thornton. Its pipeline segment along Timnath's eastern edge is less than half installed, and Thornton's own schedule runs into the middle of 2027.
The Town's notice says the closure is for the "Thornton Waterline Project." It tells drivers to plan alternate routes and allow extra travel time.
The Thornton Water Project is a buried 42-inch pipeline. It will carry water the City of Thornton bought in the 1980s through Larimer, Weld and Adams counties. That water has always been diverted from the Cache la Poudre River and used in the Water Supply and Storage Company irrigation system. Thornton says the project does not add a new diversion from the Poudre.
The pipeline is about 70 miles long. Ten miles are in Larimer County, 48 in Weld County and 12 in Adams County and Thornton. The Colorado Sun reported in May 2024 that the route starts near Ted's Place on the Poudre, northwest of Fort Collins, and crosses Larimer County farms and gravel roads into Weld County. The Sun put the cost at $485 million at that time. In 2019, the Denver Post reported an estimate of $423 million. Both figures are estimates from those years, not a final cost.
Thornton's target is to deliver the water to its customers in 2028. The project overview says construction will finish in 2028 at the earliest.
The work at Timnath's edge is Segment E. Thornton issued the contract documents in March 2025. They place the 10-mile segment along a road with several names: Weld County Road 13, Larimer County Road 1, County Line Road, Colorado Boulevard and Latham Parkway. The documents include the Latham Parkway right-of-way at the Town of Timnath boundary. According to those documents, the segment runs from near WCR 88 to Thornton's existing waterline south of WCR 68.5 in Windsor.
Thornton's November 2026 status puts Segment E under Weld County. As of that update, about 4.5 of its 10.5 miles of pipe were in the ground, all between WCR 68½ and WCR 78. Multiple crews were working on the main line and on the trenchless crossings that bore under roads. Completion is scheduled for the second quarter of 2027.
So when Colorado Boulevard reopens after Nov. 26, Segment E will still have about six miles of pipe left to install. The status of every segment shows where that fits in the whole project.
| Segment | County | Length | Status, November 2026 | Schedule |
|---|---|---|---|---|
| A | Adams/Thornton | 12 miles | 98% complete | Listed for Q3 2026 |
| B | Weld | 16 miles | Pipe installed and pressure-tested; reclamation ongoing between WCR 2 and Hwy 66 | Construction complete |
| C | Weld | 14.9 miles | 14 miles installed; 11 of 12 trenchless crossings bored | Q1 2027 |
| D | Windsor and Johnstown | About 7 miles | Constructed and tested | Completed in 2021 |
| E | Weld | 10.5 miles | About 4.5 miles installed, WCR 68½ to WCR 78 | Q2 2027 |
| F | Larimer | 10.4 miles | Design complete; county technical review of plans | Construction starts Q1 2027 |
The southern segments are nearly finished. The northern end, closest to Timnath and Fort Collins, is the least far along. Segment F is the Larimer County stretch, and it hasn't broken ground yet.
Segment F is the last segment to start because Larimer County turned down Thornton's first plan. A 2019 Larimer County staff report describes Thornton's preferred route from December 2018. It generally followed County Road 56 east to County Road 9, then ran south on LCR 1. Thornton had considered a route along Douglas Road earlier. County staff wrote that the County Road 56 route would have substantially fewer impacts than the earlier Douglas Road corridor and better potential for sharing space with other pipelines.
The county commissioners denied Thornton's 1041 permit application on Feb. 11, 2019. Thornton sued that April, arguing the county had exceeded its authority. In February 2021, the Greeley Tribune reported that a Larimer County district judge had ruled the county had the authority to deny the permit. The judge found some of the county's reasons improper but upheld the denial because the pipeline's location wasn't defined clearly enough. The Coloradoan reported in October 2022 that Thornton would not take the case to the Colorado Supreme Court.
Thornton's second application cut the Larimer County stretch from 27 miles to 10 and included other changes and concessions. Larimer County commissioners approved it on May 8, 2024, according to the Colorado Sun. Save the Poudre sued over that approval. In July 2025, the Coloradoan reported that a judge's ruling let the project keep moving.
The Larimer permit took about seven years from the first application to the final approval. That's why the segments south of Timnath are being reclaimed while the Larimer segment is still in plan review.
The Segment E contract requires the contractor to restore the surface and return work sites to "like-new conditions." Thornton's broader policy is to restore construction zones to their prior condition in consultation with property owners. That includes landscaping, fencing and access roads, as long as they are compatible with operating the pipeline.
Restoration doesn't wait for the whole segment to finish. The contract requires it on each parcel as work progresses, and it has to be complete no later than 60 days after the waterline goes in on that parcel. Reclamation can still trail the pipe. On Segment B, the pipe is installed and pressure-tested, but reclamation between WCR 2 and Highway 66 was still underway in November 2026. Thornton takes questions on its project line at 720-977-6700.
The roundabout west of Colorado Boulevard is part of a Town of Timnath project with a much closer finish date. The Timnath Parkway North Connection extends the parkway north from Buss Grove Road to Main Street, also known as County Road 5. It adds a new two-lane connection, a single-lane roundabout, a shared-use path, and improvements for pedestrians and cyclists. The Town posted its construction-start update on July 17, 2026.
This fall, the Buss Grove Road and Main Street intersection closed for construction. Traffic used a signed detour from Sept. 28 to Oct. 9, crews paved from Oct. 11 to 16, and the southbound lane reopened on Oct. 19. The Town's Nov. 6 update set that day for the new roundabout to open to two-way traffic and for the Buss Grove and Main Street intersection to reopen, weather and construction schedules permitting. The Town said the roundabout would provide an important connection to Main Street Timnath.
The work isn't completely done. The Town expects daytime lane shifts, occasional lane closures and flaggers while crews finish relocating utilities, building sidewalks and landscaping. Major roadway work is expected to be substantially complete by the end of 2026. Lighting, signs and landscaping will continue into 2027.
Both projects carry into 2027. The Town's remaining work is streetlights, signs and plantings, while Thornton's crews will still be laying main pipe on Segment E, which is scheduled to finish in the second quarter. Segment F's crews are scheduled to start in Larimer County in the first quarter of the year.
The Town's Holiday Festival is Saturday, Dec. 5, 2026, from 11 a.m. to 1 p.m. at Timnath Community Park. It will have Santa, performances, ice sculptures, an artisan market and food trucks.
When a closure like this one stays on a road through 2027, it's useful to understand what is actually being built on a block before you decide when to list or buy a home there. If you're weighing timing near Timnath's eastern edge, Beth Bishop Real Estate can help you match construction schedules like these to your own plans. Schedule Your Complimentary Home Strategy Consultation.