Timnath Built a Fiber Network It Doesn't Own, and the Address Decides Who Has It Yet

October 15, 2026

Two homes in Timnath can carry the same price, the same square footage and the same school boundary and still offer very different internet at closing. The answer depends on where the address sits in a fiber build that the Town of Timnath paid for, that the City of Loveland's Pulse utility owns, and that is still underway as of October 2026. Pulse's own monthly dashboard says that once network construction begins in a neighborhood, service typically becomes available "within six to nine months." A listing in a neighborhood where crews just finished drilling may be most of a year from a live connection.

Relocation buyers who work from home tend to treat fiber as something a house either has or lacks. In Timnath for 2026 and into 2027, it is something a house will have by a certain date, and that date comes from public council packets, not from the listing.

The Town Paid for the Build, and Loveland Owns the Network

The arrangement goes back to an intergovernmental agreement Timnath finalized with Pulse in August 2023. According to the Town of Timnath's broadband page, Timnath funds installation in phases across prioritized areas of the community, Pulse owns and operates the network and handles all customer service, and Timnath receives 25% of gross operating revenues from wired data services.

That structure explains much of how the rollout behaves. Timnath is not a customer waiting on a private carrier's business case. It is an investor that put up capital in exchange for a revenue share. When the project broke ground, BizWest reported that the revenue share was projected to return 2% to 6% on capital over 20 to 30 years, with full payback projected at 26 years.

The town's figures have shifted as the project has moved forward. In April 2025, Timnath's announcement of the first live connection, for a business customer, Dean Contracting, described a commitment of up to $20 million in Capital Improvement Funds. At the September 22, 2026 Town Council meeting, Pulse described the work as tracking under the original $17.2 million authorization, according to Citizen Portal's summary of that meeting. The public record doesn't explain how the two figures relate. The May 2026 Public Works report did say that closeout of the first two work orders had been approved, and that signatures and a $122,789.76 reimbursement payment to the town, a 4.8% savings, were in the works.

Where the Build Stands, Neighborhood by Neighborhood

At the September 22, 2026 council meeting, Pulse reported 26 of 33 initial sites complete, about 3,700 homes passed and roughly 98 miles of fiber installed, with the first phase on track for around Q1 2027, according to the meeting summary. Those are town-wide totals. The neighborhood detail is in Pulse's monthly dashboards, which are attached to council packets, and in the town's Public Works reports.

Area named in public reports Latest status in the record As of
New Timnath Ranch Construction completed April 2026 dashboard
The Ellory Under construction April 2026 dashboard
Timnath Community Park Fiber completed April 2026 dashboard
Harmony Club Fiber installation complete; site release pending final QC testing August 2026 dashboard
Wildwing Metropolitan District Directional drilling complete; vault and pothole restoration ongoing August 2026 dashboard
Feeder toward Serratoga/Kitchell Construction expected to begin within two to three weeks June 23, 2026 Public Works report
Feeder #5, Colorado Blvd. and Prospect Rd. Drilling complete; cable to follow vault QC August 2026 dashboard

The table has limits. The dashboards name the neighborhoods crews are working in, but no public list matches every Timnath subdivision to a served, waiting or later-phase status. Pulse's Timnath page embeds a construction status map and sends residents to check availability address by address. The August 2026 dashboard went into the September 22 packet, and the October 13 council agenda doesn't include a new Pulse report.

"Construction Complete" and "Service Available" Are Different Milestones

Harmony Club shows the gap. In April 2026, construction there was 75% complete. By the August dashboard, fiber installation was complete, but the site's release was still "pending final QC testing." Fiber in the ground is one milestone. Connections a household can actually order come later. Wildwing is a step further back. The June 23 Public Works report expected construction there to start "within the next couple of weeks," and by August drilling was done, with restoration still underway.

The schedule has also slipped before. The May 2026 Public Works report said progress at site 24 slowed after crews hit bedrock close to the surface, and that construction stopped in mid-May because of a conduit material shortage. Three months later, the August dashboard still said:

"Schedule to complete sites 1-30 by end of 2026 is at risk at current construction rates. Contractors are working on recovery."

The full project runs longer than the first phase. The May and June 2026 Public Works reports both list the Timnath Pulse schedule as "Construction Complete – 2027/2028." For a buyer reading a listing that says fiber is "coming," that window can run anywhere from a few weeks to a couple of years.

Why Sign-Ups Matter to the Town

Under a revenue-share agreement covering all wired data services, the town's return grows as homes and businesses subscribe. Pulse presented its take rates at the September 22 meeting, according to the meeting summary. About 19% of potential residential customers subscribe within 90 days of an area opening, about 22% at 180 days, and about 33% at sites that have been open for more than a year. The August dashboard shows 19% across the Timnath service area.

Sign-ups keep climbing well after a neighborhood goes live, and the town's 25% share of wired data revenue climbs with them. The 26-year payback projection assumed this kind of gradual adoption. Pulse also put Timnath's net promoter score at roughly 60.3 at the same meeting.

For buyers, the practical effect is that the network's operator and the town both have a reason to finish the build and sign up households in each neighborhood it reaches. That doesn't change the dates on the dashboard. It does explain why each neighborhood's status is reported in such detail month to month.

New Subdivisions Start Outside the Map

Subdivisions still on the drawing board have no place in the build schedule yet. On September 22, 2026, the Town Council approved Timnath Landing Filing 10, according to Citizen Portal's meeting summary. The town's hearing notice describes 342 lots on 79 acres south of Buss Grove Road and east of Timnath Parkway. The staff report lists utility providers for the filing but doesn't say whether, when or how those lots will get Pulse broadband. At the same meeting, council members asked Pulse about new subdivisions and the strategy for future builds, according to the meeting summary.

The April 2026 dashboard listed "construction completed in new Timnath Ranch," so new development can be added to the build. For any particular new-construction lot, though, the public record doesn't yet give an answer, so a builder presale conversation is the place to ask.

What a Buyer Can Confirm During a Showing

A few checks can pin down a timeline for a specific address.

  1. Check the exact address on Pulse's Timnath availability tool. Do this before the inspection period ends, and use the lot or unit address, not the subdivision name.
  2. Find the neighborhood in the latest dashboard in the Town Council packet. The August 2026 report was attached to the September 22 packet.
  3. Work out whether the address falls in an area where construction is complete, underway, or not yet started. The six-to-nine-month estimate starts at construction, not at the dashboard update.
  4. For new construction, ask the builder in writing what broadband is planned for the filing, since staff reports like the one for Timnath Landing Filing 10 don't specify it.

Once an address can be served, Pulse's posted Timnath plans range from Fiber 500 at $50 a month to Future Fiber, a 10 Gig tier, at $179, with Smart Fiber at 1 Gig for $75, Power Fiber at 2 Gig for $99 and Ultra Fiber at 4 Gig for $129. All prices assume ACH autopay. Pulse says installation is free, a router is included, there are no data caps, and customers can cancel without penalty after 90 days.

A Few Straight Answers

What are the options while an address waits for Pulse? Xfinity markets service in Timnath. Pulse's own comparison page, using competitor information as of September 22, 2025, says CenturyLink DSL at around 100 Mbps appeared to be available across Timnath ZIP codes and that Quantum Fiber was not available in Timnath then. That comes from Pulse's own comparison, so a buyer would want to confirm current offers with each provider.

When did the first Timnath connection go live? The town announced its first Pulse customer, Dean Contracting, in April 2025.

Does the town operate the internet service? No. Under the 2023 agreement, Pulse owns and operates the network and handles all customer service. Timnath provides phased funding and receives 25% of gross wired data revenue.